2006
July 31st - Contractors beginning preparations to install fencing and safety covered walkways around the construction site.
August 9th - Modular units installed to provide supplemental classroom and office space during the construction.
August 17th - Several new classrooms added to provide additional space during the renovation. (Read More)
2007
General Construction
- Overall project is approx. 25% complete. Occupancy still scheduled for Fall Classes of 2008. Actual move-in to be coordinated through Academic Affairs.
- 95% of demo work complete. (Some misc. core drilling still outstanding).
- Hazardous Material abatement work is 97% complete.
- Structural seismic strenghting of concrete shear walls is 95% complete.
- New HVAC, plumbing, electrical systems have started to be installed.
- New door openings are complete.
- New interior wall framing is 10% complete.
- New elevator shaft walls are complete at this time.
Spring- Most demolition work completed. Layout of new mechanical, electrical and plumbing systems begins.
Group II Furniture & Equipment Status
- June/July- Campus waiting for Sacramento / Chancellor's Office preliminary funding approval
- September/October- Formal approval
Retain Group II consultant - Fall 2007 Commence procurement end of
2007 beginning of 2008.
- December- Work with departments to confirm Furniture and Equipment requests
2008
- January/February- Work with departments to obtain F&E quotes
- March- Confirm quotes and commence F&E procurement
- Spring/Summer- New furniture and equipment arrives and is delivered into building 3.
- Summer- Renovation Completed. Departments move any stored equipment out of surge storage and into building 3.
- Fall 2008- Classes begin in Renovated Building 3